Railways’ bio-toilet project deeply flawed
The Comptroller and Auditor General found 1,99,689 defects in 25,000 bio-toilets
Indian Railways have not adhered to the guidelines on testing the effluents released by bio-toilets
‘Nexus of bureaucrats and industrialists’ was pushing for what was ‘nothing but gobar gas plants involving no technology’
There is no clarity on critical issues relating to bio-toilets on trains, Need 3,350 truckloads of cow dung at Rs 42 cr, reveals CAG report
New Delhi: The Indian Railways needs to buy 3,350 truckloads of cow dung at Rs 42 crore in 2018 to ‘recharge’ – add bacteria to activate degradation – leaky, malfunctioning ‘bio-toilets’ that it has fitted on 44.8 percent of trains and hopes to expand to all trains by 2018, according to IndiaSpend projections of data released by the national auditor to Parliament.
Bio-toilets are small-scale sewage-treatment systems beneath the toilet seat: Bacteria in a compost chamber digest human excreta, leaving behind water and methane. That’s how they were supposed to work.
The Comptroller and Auditor General’s (CAG) report on these bio-toilets echo the findings of November 2017 investigation into their widespread malfunctioning: The CAG found 1,99,689 defects in 25,000 toilets.
Representational image. Reuters
Responding to the CAG findings, the Ministry of Railways said its criticism was ‘not correct’ and that ‘some problems of choking were occurring on account of misuse of toilets by passengers.’ An official note from 20 December 2017, said: ‘These issues are being dealt with promptly.’
‘By November 2011, the performance issues of each design of bio-toilets were clearly showing up,’ the note said. ‘Therefore, the ministry did not wait until the end of the trial period to make the decision (to order the procurement of bio-toilets from private manufacturers).’ Studies from the Indian Institute of Technology (IIT) Madras and IIT Kanpur that said the bio-toilets were no better than ‘septic tanks’ and the water they let out no better than ‘raw sewage’.
Each bio-toilet requires 60 liters – or three large bucketfuls – of inoculum, a mix of cow dung and water, according to the 19 December 2017, CAG report. This inoculum begins the process of breaking down 3,980 tons of human excreta that is released untreated by trains on railway tracks nationwide every day.
The bio-toilets originally used a bacterium found in Antarctica by a defense scientist, who cultured it in 2005 and 10 years later, got a patent on its use. Over seven years to 2017, 97,761 such toilets were fitted in new coaches or retrofitted in existing Indian trains.
The Railways went ahead with the toilet installation even though the flaw in the basic model designed by the Defence Research and Development Organisation (DRDO) had been pointed out by an expert panel in 2007. In an interview, Vinod Tare, an IIT professor of environmental engineering, who headed this panel, told that these bio-toilets had been found ineffective at two venues: Kumbh Mela, the massive gathering of Hindu pilgrims held every 12 years at a river bank and the army base-camp at Siachen glacier.
The panel’s two-year study was completed in November 2017 by IIT Madras, as IndiaSpend reported on 23 November 2017.
The Railways sent a rejoinder – which can be read here – and soon after announced they were exploring airplane-style vacuum toilets.
The Railways bought 3,600 liters of inoculum for Rs 68,400 in May 2016, said the CAG report. Based on this cost, it is estimated that to recharge the 97,761 bio-toilets currently in use, the Railways will need 23.46 million litres – or 3,350 truckloads – of cow dung.
With the Railways failing to produce enough bacteria, the cow dung will be sourced from the private sector at Rs 19 per litre. The Railways have a workshop – with an installed capacity to generate 30,000 liters of bacteria each month – in Nagpur, but no action has been taken on a 2011 proposal to set up two more facilities, at Kapurthala and Perambur.
No clarity on funds or manpower for bio-toilet project
There is no clarity on two other critical issues relating to bio-toilets on trains: The infrastructure costs involved in the installation, including procurement and installation of evacuation machines and hydraulic lifts, and anticipated expenses on training and deployment of manpower.
Further, if all 54,506 rail coaches are to be fitted with vacuum toilets atop the bio-toilets being installed – as is being planned – there will be an additional cost of Rs 10,900 crore. The current market price of a vacuum toilet unit is approximately Rs 2,00,000.
The additional expense might have been worth it if the bio-toilet scheme, 24 years in the making, had been efficient. But the CAG has amplified concerns about its performance and has endorsed the findings of the IndiaSpend investigation.
Flaws in bio-toilets
In an evaluation of 25,000 toilets for the period under review (2016-17), the CAG detected 1,99,689 defects and deficiencies. Here are some major issues, according to the report:
* Highest number of problems/defects (41,111) found at the Bengaluru coaching depot, followed by Gorakhpur (24,495) and Wadi Bunder (22,521);
* Complaints per bio-toilet were highest at the Bengaluru coaching deport (98), followed by Wadi Bunder (32), Rameshwaram (28) and Gwalior (17);
* Of the 1,02,792 instances of choking, 10,098 (10%) cases reported in March 2017;
* Of the 1,02,792 cases of choking in 25,080 bio-toilets, the highest (34%) were reported from Bengaluru. This implied that one bio-toilet got choked 83 times a year;
* Choking incidents have risen from 2015-16: One bio-toilet got choked four times a year during 2016-17.
CAG criticises quantity and quality of material used
Then-defense minister Manohar Parrikar, Y. Ashok Babu, a scientist at the DRDO, had alleged that a ‘nexus of bureaucrats and industrialists’ was pushing for what was ‘nothing but gobar gas plants involving no technology’.
The CAG report too slammed the Railways for the ‘quality and quantity’ of material being procured.
As the report observed, there were complaints pending against seven of the nine firms against with which the Railway Board placed orders.
These are M/s JSL Life Style Limited, M/s Omax Auto Limited, M/s Mohan Rail Components Limited, M/s Rail Fab, M/s Hindustan Fiber Glass Works and M/s Rail Tech. etc.
In July 2017, the Ministry of Railways barred three companies (M/s Rail Tech, M/s Rail Fab and M/s Hindustan Fiber) from being considered for railway contracts for an unspecified period. The ministry also proposed that the contract of another company, M/s Mohan Rail, be canceled.
Negligence in testing of effluents and bacteria culture
The CAG report found that 12 coaching depots of nine railway zones had not finalized the annual maintenance and operating contracts (AMOCs) for bio-toilets.
‘Evaluation of performance is a continuous process resulting in addition or deletion from the approved list,’ the Ministry of Railways said in a press note in response to the CAG report. It added that ‘all major coaching depots now had the AMOC contract, while this was progressively being extended to other depots’.
As the CAG found, Indian Railways have not adhered to the guidelines on testing the effluents released by bio-toilets. The tests had not been conducted at all at the Dhanbad coaching depot and records of the samples sent for testing and the results of these tests were not maintained at five coaching depots.
At the Lower Parel workshop in Mumbai, 18 drums of bacteria procured at a cost of Rs 68,400 in May 2016 had been lying unused even after their shelf life had expired.
After 2011, the Railways placed bulk orders for the supply, installation, and commissioning of approximately 80,000 bio-toilets. The CAG criticised the Railways for failing to come up with a ‘standardized design’ for these units. It also pointed to the ‘large-scale proliferation’ of 10,000 tanks in November 2011 ‘before test results of trials on seven different variants had been analyzed’.
Earlier suggested that the land-based variants of these toilets were unsuccessful.